New Year Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

AACE International Updated PSP Exam Questions and Answers by lainey

Page: 11 / 11

AACE International PSP Exam Overview :

Exam Name: Planning & Scheduling Professional (PSP) Exam
Exam Code: PSP Dumps
Vendor: AACE International Certification: Professional Level
Questions: 163 Q&A's Shared By: lainey
Question 44

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Questions 44

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Discussion
Question 45

Which of the following parties is NOT a stakeholder of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Discussion
Question 46

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Options:

A.

3.9% (1 : 25.708)

B.

2.3% (1 : 43.501).

C.

9.1% (1 : 11.000).

D.

8.6% (1 : 11.591)

Discussion
Question 47

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

Questions 47

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Questions 47

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 3, 2024
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Robin
Cramkey is highly recommended.
Jonah Oct 16, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Madeleine
Passed my exam with my dream scoreā€¦. Guys do give these dumps a try. They are authentic.
Ziggy Sep 3, 2024
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Page: 11 / 11

PSP
PDF

$36.75  $104.99

PSP Testing Engine

$43.75  $124.99

PSP PDF + Testing Engine

$57.75  $164.99