Question 24

The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open

Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.

At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.

However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video

tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of

storage space on the company server and require minimal maintenance.

The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.

Remember to limit your answers to the number of selections requested in each question.

Which 2 individuals should the Facilitator invite to participate in the Workshop?

Options:

A.

Chief Executive (Steering Group)

B.

Representative for Earth Excavations (Solution Developer)

C.

Representative for Timber Tigers (Solution Developer)

D.

IT Operations Manager (Solution Development Team)

E.

Marketing Director (Business Visionary)

Discussion
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 22, 2024
That's great to hear. I am going to try them soon.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Question 25

Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Questions 25

Assertion:-

1. The rooms and facilities must be deployed into live use at the end of each Timebox.

BECAUSE

Reason:

Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.

2. The tasks associated with each Solution Development Timebox should be included

in the Delivery Plan.

BECAUSE

Reason:

A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.

3. The development approach should have been agreed during Foundations.

BECAUSE

Reason:

The Development Approach Definition must be created before Evolutionary

Development can commence.

4. The resources from Timber Tigers and Earth Excavations should have been engaged

before the start of Evolutionary Development.

BECAUSE

Reason:

Commitment to delivery is based on pre-agreed resource levels at the project level.

5. A final Deployment phase should be held after Timebox C has completed.

BECAUSE

Reason:

The Deployed Solution is assessed post-project to confirm whether the expected benefits have been

achieved.

Questions 25

Questions 25

Options:

Discussion
Question 26

How should the Project Manager assist the electricians to deliver the wiring?

Options:

A.

Provide separate electricians' rooms so they can focus on their work.

B.

Hold a weekly meeting for electricians so they can report on progress.

C.

Encourage the Business Ambassador to be available to discuss location of electrical sockets.

D.

Produce a detailed design of all electrical socket locations, to be approved by the Technical Co-ordinator.

Discussion
Question 27

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

Options:

A.

Present own interpretation of what the system should include.

B.

Present the group with a predefined specification of what should be included.

C.

Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

D.

Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.

E.

Prepare a report describing the outcome of the workshop.