Exam Name: | Agile Project Management (AgilePM) Practitioner Exam | ||
Exam Code: | AgilePM-Practitioner Dumps | ||
Vendor: | APMG-International | Certification: | AgilePM |
Questions: | 78 Q&A's | Shared By: | evangeline |
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.
The Business Ambassador assigned to the project is only available 2 days a
week. The Project Manager has stated that the Investigation stage for each
Timebox should, where possible, be planned around the availability of the
Business Ambassador.
Is this an appropriate application of the DSDM lifecycle?
An external web developer is to be contracted to create the new coffee bar
insurance area on the existing web site. The chosen web developer will only
agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?
Which 2 actions should the Workshop Facilitator take to implement the new
Must Have requirement?