Question 20

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Discussion
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza May 16, 2026
That makes sense. What makes Cramkey Dumps different from other study materials?
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia May 28, 2026
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden May 7, 2026
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander May 15, 2026
Thanks for the recommendation! I'll check it out.
Question 21

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

Options:

A.

Present own interpretation of what the system should include.

B.

Present the group with a predefined specification of what should be included.

C.

Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

D.

Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.

E.

Prepare a report describing the outcome of the workshop.

Discussion
Question 22

What action should the Project Manager take during the Close-Out of Timebox C?

Options:

A.

Remove ' Aspects ' from the supplier list for all future projects.

B.

Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.

C.

Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.

D.

Initiate the work required to complete the windows to the required standard.

Discussion
Question 23

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

Options:

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Discussion