Question 8

Who defines the amount of work to be completed during an iteration?

Options:

A.

The product owner based on their estimation of what should be done.

B.

The team lead who is responsible for ensuring that the work gets done.

C.

The team members based on their understanding of the team's current capacity.

D.

The quality tester based on their estimation of how much completed work can be tested.

Discussion
Question 9

True or False: Process goals are meant to prescribe how to achieve a particular objective for a team

Options:

A.

True

B.

False

Discussion
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Sep 25, 2024
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Question 10

If you can measure only one thing you should measure the cost of delay. This is reflected in which of the following principles of DA?

Options:

A.

Keep workloads within capacity

B.

Accelerate value delivery

C.

Collaborate proactively

D.

Optimize flow

Discussion
Question 11

The Marketing process blade is responsible for crafting an appealing roadmap of the organization's offerings in close conjunction with:

Options:

A.

Portfolio management

B.

Product management

C.

Finance

D.

Business Operations

E.

Control