Question 12

A scrum master needs to set up a team for a long-term project that has the potential for significant budgeting and tracking overhead. What type of team should the scrum master set up?

Options:

A.

A long-standing team

B.

A cross-functional team

C.

A project team

D.

A shared services team

Discussion
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 25, 2024
Good point. Thanks for the advice. I'll definitely keep that in mind.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Oct 5, 2024
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 13

The architecture of a product is usually proven in which phase of a project?

Options:

A.

Elaboration

B.

Construction

C.

Inception

D.

Transition

Discussion
Question 14

How should iterations for an agile project be planned?

Options:

A.

At the beginning of each iteration by pulling from product backlog.

B.

Iteratively by the product owner to ensure global optimization.

C.

Throughout the project by using iteration reviews to continuously improve quality.

D.

At the retrospective meetings to ensure nothing is missed from one iteration to the next.

Discussion
Question 15

Which of the following is false about the Business Operations process blade?

Options:

A.

It requires close collaboration with the Sales and Marketing process blades

B.

It involves strategies for providing services to the business

C.

The implementation of this blade will be standard across domains

D.

It should focus on delighting the customers

Discussion