Over the period of 2 to 3 weeks, a cluster displays the following:
•Periods where Warning Alerts of memory usage over 75% are asserted
•Periods where Critical Warnings of memory usage over 90% are asserted
•Periods of slow of frozen VDI desktops have caused work stoppage or slowdown
•VDI clones have periodically not powered up when called, causing work stoppage
Which steps should be used to prioritize the administrator’s troubleshooting efforts?
An administrator needs to create and start five new VMs for a Data Analytics Project (OLAP). The VM Profile is as follows:
• vCPU:4
• vRAM: 64 GB
• vDisk: 1.5 TB
Each of the four nodes of the Nutanix cluster has the following:
• 24 vCPU. 20% overall usage
• 192 GB RAM, 60% overall usage
• 2xl920GBSSD
• 4x 2 TB HDD
At cluster level, there is a single RF2 container that is 30% utilized and has an extent store capacity of 13.5 TB.
Which component requires administrator attention?
A customer already has a Prism Central (PC) instance deployed in their environment and expects the consultant to unregister the old cluster before registering the new cluster
What steps should the consultant take to safely and successfully unregister the customer's former cluster from PC?
A consultant successfully completes a Foundation using a flat switch. The consultant then works with the customer to move the cluster over to their production network. After the move, the CVMs and hypervisors can no longer communicate, which prevents the cluster from starting.
Which option should be used to resolve this issue?