Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit
The introduction of reviews and inspections has often failed as a process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail. 2 Credits (for 2 out of 3 correct 1 credit)