Question 12

In which stage of the data center life cycle does commissioning take place?

Options:

A.

Retire

B.

Operate/optimize

C.

Implement

D.

Design

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 16, 2024
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Question 13

Do you need to consider blast protection when designing a data center?

Options:

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Discussion
Question 14

You are allowed to use a calculator for this question.

A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.

The temperature is 20 °C / 68 °F.

The required design concentration is 7%.

The S-Factor is 0.1359 (metric) / 1.885 (imperial).

Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

Options:

A.

Approximately 410 kg / 900 lbs

B.

Approximately 820 kg / 1,800 lbs

C.

Approximately 1,390 kg / 3,000 lbs

D.

Approximately 1,640 kg / 3,600 lbs

Discussion
Question 15

What is the main reason to install Earth Leakage protection?

Options:

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Discussion