Exam Name: | EXIN EPI Certified Data Centre Specialist | ||
Exam Code: | CDCS Dumps | ||
Vendor: | Exin | Certification: | EPI Data Centre |
Questions: | 60 Q&A's | Shared By: | aylin |
In which stage of the data center life cycle does commissioning take place?
You are allowed to use a calculator for this question.
A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.
The temperature is 20 °C / 68 °F.
The required design concentration is 7%.
The S-Factor is 0.1359 (metric) / 1.885 (imperial).
Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?