Question 12

In which stage of the data center life cycle does commissioning take place?

Options:

A.

Retire

B.

Operate/optimize

C.

Implement

D.

Design

Discussion
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Aug 29, 2024
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 13

Do you need to consider blast protection when designing a data center?

Options:

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Discussion
Question 14

You are allowed to use a calculator for this question.

A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.

The temperature is 20 °C / 68 °F.

The required design concentration is 7%.

The S-Factor is 0.1359 (metric) / 1.885 (imperial).

Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

Options:

A.

Approximately 410 kg / 900 lbs

B.

Approximately 820 kg / 1,800 lbs

C.

Approximately 1,390 kg / 3,000 lbs

D.

Approximately 1,640 kg / 3,600 lbs

Discussion
Question 15

What is the main reason to install Earth Leakage protection?

Options:

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Discussion