Question 12

The performance of a production manager is assessed on efficient use of materials during the production process.

Actual data and data from the fixed budget for Month 4 are as follows:

Questions 12

What figures should be compared in order to assess the production manager's performance for Month 4?

Options:

A.

15,500 kg and 11,000 kg

B.

15,500 kg and 14,000 kg

C.

16,500 kg and 16,000 kg

D.

11,000 kg and 14,000 kg

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Question 13

ABC uses an activity-based costing system.

The company manufactures three products, details of which are given below:

Questions 13

Total material movement costs for the period are $10,000.

The material movement cost per unit for Product Z (to the nearest $0.01) is:

Options:

A.

$10.67

B.

$2.71

C.

$3.23

D.

$7.62

Discussion
Question 14

QR uses an activity based budgeting (ABB) system to budget product costs. It manufactures two products, product Q and product R. The budget details for these two products for the forthcoming period are as follows:

Questions 14

The total budgeted cost of setting up the machines is $74,400.

What was the budgeted machine set up cost per unit of product Q?

Options:

A.

$0.39 per unit

B.

$0.56 per unit

C.

$0.37 per unit

D.

$0.48 per unit

Discussion
Question 15

When classifying quality costs, which of the following is NOT likely to be an appraisal cost?

Options:

A.

Cost of product liability insurance

B.

Cost of supervision of testing and inspection activities

C.

Performance testing costs

D.

Cost of maintaining inspection equipment

Discussion