To help you prepare for the C_TS422_2020 SAP exam, we are offering free C_TS422_2020 SAP exam questions. All you need to do is sign up, provide your details, and prepare with the free C_TS422_2020 practice questions. Once you have done that, you will have access to the entire pool of SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2020 test questions which will help you better prepare for the exam. Additionally, you can also find a range of SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing resources online to help you better understand the topics covered on the exam, such as SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2020 video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic SAP C_TS422_2020 exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? Note: There are 2 correct answers to this question.

Options:

A.  

Model a handling resource in the location master and goods receipt time in the mater all master.

B.  

Model a separate resource in the production data structure.

C.  

Model a resource inbound in the location master.

D.  

Model a transportation resource in the location master.

Discussion 0
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Aug 31, 2024
Agreeā€¦.Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Aug 30, 2024
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Questions 3

Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.  

Run MRP with automatic selection of production version.

B.  

Run PP/DS heuristics for repetitive manufacturing.

C.  

Run MRP with quota arrangement.

D.  

Assign planned orders manual lying the planning table.

Discussion 0
Questions 4

What does it mean for the production planner when MRP works with infinite capacities?

Options:

A.  

MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

B.  

MRP creates capacity requirements without checking the capacity of a work center.

C.  

MRP creates capacity requirements only if the work center has sufficient capacity.

D.  

MRP assigns capacity requirements automatically after the last scheduled order on a work center.

Discussion 0
Questions 5

Which task list types can have parallel sequences? There are 2 correct answers to this question.

Options:

A.  

Routings (N)

B.  

Master recipes (2)

C.  

Rate routings (R)

D.  

Reference operation sets (S)