Question 12

Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Run MRP with automatic selection of production version.

B.

Run PP/DS heuristics for repetitive manufacturing.

C.

Run MRP with quota arrangement.

D.

Assign planned orders manual lying the planning table.

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Question 13

MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

Options:

A.

It is converted into a production order.

B.

It is converted into a reservation.

C.

It is converted into a planned order.

D.

It is converted into a schedule line.

Discussion
Question 14

You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.

Options:

A.

Full conversion

B.

Order release

C.

Individual conversion

D.

Partial conversion

Discussion
Question 15

How Is the bill of material (BOM) exploded when you use a BOM explosion number?

Options:

A.

With respect to a defined separate change status for product and each assembly

B.

With respect to a common change status for product and each assembly

C.

With respect to defined separate key dates for product and each assembly

D.

With respect to a common key date for product and each assembly

Discussion