Certified Tester Advanced Level Test Manager (CTAL-TM)
Last Update Dec 22, 2024
Total Questions : 65
To help you prepare for the CTAL-TM ISTQB exam, we are offering free CTAL-TM ISTQB exam questions. All you need to do is sign up, provide your details, and prepare with the free CTAL-TM practice questions. Once you have done that, you will have access to the entire pool of Certified Tester Advanced Level Test Manager (CTAL-TM) CTAL-TM test questions which will help you better prepare for the exam. Additionally, you can also find a range of Certified Tester Advanced Level Test Manager (CTAL-TM) resources online to help you better understand the topics covered on the exam, such as Certified Tester Advanced Level Test Manager (CTAL-TM) CTAL-TM video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic ISTQB CTAL-TM exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.
Which of the following should be considered the biggest risk to the schedule when trying to implement formal scripted test cases early in the SDLC for a system with a
large GUI front end? [2]
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the
project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,
particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as
"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.
Given this information, which lifecycle model should you recommend?[3]