Winter Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

Page: 1 / 2

ISTQB Test Manager ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]

ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]

Last Update Nov 22, 2024
Total Questions : 64

To help you prepare for the ATM ISTQB exam, we are offering free ATM ISTQB exam questions. All you need to do is sign up, provide your details, and prepare with the free ATM practice questions. Once you have done that, you will have access to the entire pool of ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] ATM test questions which will help you better prepare for the exam. Additionally, you can also find a range of ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] resources online to help you better understand the topics covered on the exam, such as ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] ATM video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic ISTQB ATM exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

Assume you are managing a test automation project for a mission-critical system.

Because vendor provided tools and open source solutions don't meet the needs of this project, you ask your test team to develop a custom automation framework.

Which of the following management issues associated to the development of this custom automation framework is least likely to manage?

K2 1 credit

Options:

A.  

Proper testing for the custom automation framework must be performed

B.  

The custom automation framework will require an adequate documentation

C.  

The changes to the custom automation framework should be communicated to all external users of this tool under the GNU license

D.  

The custom automation framework will need proper maintenance

Discussion 0
Questions 3

After a selection process you have selected a test management tool that is going be introduced in your organization and used by your test team in a pilot project.

You have already identified the member of your test team who will be the administrator of the tool, since he/she has a significant experience with the administration of test management tools and so he/she is able to make effective and efficient up-front decisions about "how" the tool will be used. You have also developed a training plan for the other members of your test team.

In collaboration with the administrator of the tool you have also devised standard ways of managing, storing and maintaining the tool and its assets including backup/restore procedures.

You have also analyzed standard formats supported by the tool (CSV, XLS, XML, etc.) to export, import and archive all the information managed by the tool itself (requirements, test case specifications, test plans etc.) for compliance with the most important test management tools, in order to minimize the impacts of migrating this information to a new tool that could replace the existing one in the future.

Which of the following phases in the lifecycle of the new tool has NOT been adequately considered in this description?

K2 1 credit

Options:

A.  

Acquisition

B.  

Support and maintenance

C.  

Evolution

D.  

Retirement

Discussion 0
Questions 4

Assume you are the Test Manager for a new software release of an e-commerce application.

The server farm consists of six servers providing different capabilities. Each capability is provided through a set of web services.

The requirements specification document contains several SLAs

(Service Level Agreements) like the following:

SLA-001: 99.5 percent of all transactions shall have a response time less than five seconds under a load of up-to 5000 concurrent users

The main objective is to assure that all the SLAs specified in the requirements specification document will be met before system release. You decide to apply a risk-based testing strategy and an early risk analysis confirms that performance is high risk. You can count on a well-written requirements specification and on a model of the system behavior under various load levels produced by the system architect.

Which of the following test activities would you expect to be the less important ones to achieve the test objectives in this scenario?

K4 3 credits

Options:

A.  

Perform unit performance testing for each single web service

B.  

Monitor the SLAs after the system has been released into the production environment

C.  

Perform system performance testing, consisting of several performance testing sessions, to verify if all the SLAs have been met

D.  

Perform static performance testing by reviewing the architectural model of the system under various load levels

Discussion 0
Questions 5

An agile development team decides to hire a tester who has always workeD.

- in independent test teams, reporting the problems found in a defect tracking system

- in safety-critical projects, with a stronger focus on the quality of the product than on time and budget.

This agile team is focused on short-term goals to get the product released on time and within budget.

Which of the following answers would you expect to be most likely true in this scenario?

K2 1 credit

Options:

A.  

Agile teams like the presence of a tester in their teams and the tester will be able to adapt to the new context without any issue

B.  

The developers will immediately follow the guidelines described by the tester

C.  

The tester can continue to report the problems found in a defect tracking system and be more focused on the quality than on time and budget constraints

D.  

The tester’s mission could be to verify adherence to requirements, instead of reporting formally the problems in a defect tracking system

Discussion 0
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 26, 2024
That's great to know. So, you think new students should buy these dumps?
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.

ATM
PDF

$40  $99.99

ATM Testing Engine

$48  $119.99

ATM PDF + Testing Engine

$64  $159.99