ISTQB Test Manager Advanced Test Management Exam v 3.0 – ISTQB

Advanced Test Management Exam v 3.0 – ISTQB

Last Update Nov 25, 2025
Total Questions : 50

To help you prepare for the ATM ISTQB exam, we are offering free ATM ISTQB exam questions. All you need to do is sign up, provide your details, and prepare with the free ATM practice questions. Once you have done that, you will have access to the entire pool of Advanced Test Management Exam v 3.0 – ISTQB ATM test questions which will help you better prepare for the exam. Additionally, you can also find a range of Advanced Test Management Exam v 3.0 – ISTQB resources online to help you better understand the topics covered on the exam, such as Advanced Test Management Exam v 3.0 – ISTQB ATM video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic ISTQB ATM exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

Your team has been working on anAgile project for two months.There is a retrospective at the end of each sprint One of the data items reviewed is how many defects are being caught by users rather than bytesters.The test team is being blamed for these escapes

What do you need to do to make these sessions more productive?

Options:

A.  

You should attend the retrospective instead of the individual testers

B.  

You should do root cause analysis to prove the developers are responsible

C.  

You should gather metrics to present to the team regarding all the hours spent testing

D.  

You should help the team brainstorm ideas on how to improve the testing to eliminate the escapes

Discussion 0
Questions 3

Which of the following is the proper order for the stages of a toollifecycle?

Options:

A.  

Acquisition Support Evolution Retirement

B.  

Acquisition Evolution Support Retirement

C.  

Evolution Acquisition Retirement Support

D.  

Evolution Support Acquisition Retirement

Discussion 0
Questions 4

You have been asked to make a recommendation on deployment readiness on the software your team has been testing.You have the following metrics:

Questions 4

Given this information what is a critical metric you are missing?

Options:

A.  

Number of tests passed

B.  

Number of defects outstanding

C.  

Residual risk

D.  

Planned vs actual cost of testing

Discussion 0
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Oct 10, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Oct 23, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Oct 24, 2025
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Oct 6, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Questions 5

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?

Options:

A.  

Function points

B.  

Extrapolation

C.  

Planning poker

D.  

Three-point estimation