Question 36

Cooling tower blowdown is necessary because

Options:

A.

too much water in the system is inefficient so its water levels must be lowered

B.

a buildup of dissolved solids increases conductivity which decreases efficiency

C.

excess water treatment chemical levels corrode pipes and bleed-off reduces chemical levels

D.

cold temperatures can freeze pipes if water is not moved and bleed-off prevents that from happening

Discussion
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Oct 22, 2024
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Question 37

Which of the following strategies improves cooling tower water efficiency?

Options:

A.

Increase cooling tower fan speed

B.

Increase the cooling tower blowdown

C.

Install and maintain a conductivity meter

D.

Lower set point of water leaving cooling tower

Discussion
Question 38

Using the following table, the number of cooling tower cycles in Water Efficiency Credit, Cooling Tower Water Use is determined by which five parameters in the rating system?(Click on Exhibit)

Options:

A.

All of the five parameters summed together

B.

All of the five parameters subtracted from the maximum concentration level

C.

Whichever of the five parameters has the fewest calculated cycles of concentration without exceeding the maximum level for the parameter

D.

Whichever of the five parameters has the greatest calculated cycles of concentration without exceeding the maximum level for the parameter

Discussion
Question 39

At what point is it appropriate for the LEED AP to administer an alternative transportation survey to those that visit the building?

Options:

A.

When 50% of visitors utilize alternative transportation modes to visit the building

B.

When 80% of visitors utilize alternative transportation modes to visit the building

C.

When the daily average or typical peak number of visitors is at least 50% of the regular building occupants

D.

When the daily average or typical peak number of visitors is greater than the number of regular buildingoccupants

Discussion