Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

USGBC Updated LEED-AP-O+M Exam Questions and Answers by niam

Page: 9 / 12

USGBC LEED-AP-O+M Exam Overview :

Exam Name: LEED AP Operations + Maintenance (LEED AP O+M)
Exam Code: LEED-AP-O+M Dumps
Vendor: USGBC Certification: Leadership in Energy and Environmental Design (LEED)
Questions: 166 Q&A's Shared By: niam
Question 36

Cooling tower blowdown is necessary because

Options:

A.

too much water in the system is inefficient so its water levels must be lowered

B.

a buildup of dissolved solids increases conductivity which decreases efficiency

C.

excess water treatment chemical levels corrode pipes and bleed-off reduces chemical levels

D.

cold temperatures can freeze pipes if water is not moved and bleed-off prevents that from happening

Discussion
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Question 37

Which of the following strategies improves cooling tower water efficiency?

Options:

A.

Increase cooling tower fan speed

B.

Increase the cooling tower blowdown

C.

Install and maintain a conductivity meter

D.

Lower set point of water leaving cooling tower

Discussion
Question 38

Using the following table, the number of cooling tower cycles in Water Efficiency Credit, Cooling Tower Water Use is determined by which five parameters in the rating system?(Click on Exhibit)

Options:

A.

All of the five parameters summed together

B.

All of the five parameters subtracted from the maximum concentration level

C.

Whichever of the five parameters has the fewest calculated cycles of concentration without exceeding the maximum level for the parameter

D.

Whichever of the five parameters has the greatest calculated cycles of concentration without exceeding the maximum level for the parameter

Discussion
Question 39

At what point is it appropriate for the LEED AP to administer an alternative transportation survey to those that visit the building?

Options:

A.

When 50% of visitors utilize alternative transportation modes to visit the building

B.

When 80% of visitors utilize alternative transportation modes to visit the building

C.

When the daily average or typical peak number of visitors is at least 50% of the regular building occupants

D.

When the daily average or typical peak number of visitors is greater than the number of regular buildingoccupants

Discussion
Page: 9 / 12

LEED-AP-O+M
PDF

$36.75  $104.99

LEED-AP-O+M Testing Engine

$43.75  $124.99

LEED-AP-O+M PDF + Testing Engine

$57.75  $164.99