Question 16

When determining the ordering of an item on the Product Backlog, what are some things a Product Owner should consider?

(choose the best four answers)

Options:

A.

Alignment with organizational strategy and goals.

B.

The techniques the Developers will use to implement the item.

C.

Risk. For example; business risk, market risk, or technology risk.

D.

Alignment with other Product Backlog items.

E.

Importance to users or customers.

Discussion
Question 17

A Sprint forecast is:

(choose the best answer)

Options:

A.

A commitment the Developers makes to deliver a particular set of Product Backlog

items.

B.

Useful for the stakeholders to know what will be included in future releases.

C.

The amount of work the Developers believe they can complete in that Sprint.

D.

A useful tool for management to understand team performance and capacity.

Discussion
Question 18

Your executive leadership team believes that your product can achieve higher market share.

. The Sales Leader is pressuring you to reduce the price of the product to

attract more customers.

. The Director of Finance is concerned that reducing the price will merely

reduce the product's profitability.

What sources of information should you consider when deciding whether to drop the price as

the Sales Leader is suggesting?

(choose the best four answers)

Options:

A.

Channel sales strategy.

B.

Customer satisfaction.

C.

Market share.

D.

Unmet customer needs.

E.

Competitor pricing.

F.

Company earnings targets.

Discussion
Question 19

When should the Product Owner update the project plan?

(choose the best answer)

Options:

A.

After the Daily Scrum to ensure an accurate daily overview of project progress.

B.

The project plan must be updated prior to the Sprint Retrospective.

C.

The Product Backlog is the plan in Scrum. It is updated as new information and

insights emerge.

D.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Mar 7, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Mar 26, 2026
did you use PDF or Engine? Which one is most useful?
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Mar 4, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Mar 9, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Mar 4, 2026
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Page: 4 / 5

PSPO-II
PDF

$36.75  $104.99

PSPO-II Testing Engine

$43.75  $124.99

PSPO-II PDF + Testing Engine

$57.75  $164.99