Question 52

During which PI planning activity are Stories written and sequenced?

Options:

A.

The team breakout session

B.

The draft plan review

C.

The management Review and Problem-Solving workshop

D.

The business context presentation

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Question 53

Quality is first and foremost a function of what in a Lean-Agile concept?

Options:

A.

Preserving options

B.

Culture of shared responsibility

C.

Empowered Solution authority

D.

Deployment on demand

Discussion
Question 54

The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What best describes the next step for the Epic?

Options:

A.

It will be implemented once the Epic Owner approves the Lean business case.

B.

It will be moved to the ready state in the Portfolio Kanban if it receives a 'go' decision from Lean Portfolio Management.

C.

It will remain in the analyzing step until one or more Agile Release Trains have the capacity to implement it.

D.

It will be implemented if it has the highest weighted shortest job first (WSJF) ranking

Discussion
Question 55

What does the "C" represent in the CALMR approach to DevOps?

Options:

A.

Completion

B.

Cycle-time

C.

Culture

D.

Continuous Integration

Discussion
Page: 13 / 19
Title
Questions
Posted

SP-SAFe-Practitioner
PDF

$36.75  $104.99

SP-SAFe-Practitioner Testing Engine

$43.75  $124.99

SP-SAFe-Practitioner PDF + Testing Engine

$57.75  $164.99