Question 8

You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.

What could be the reason for this?

NOTE: There are2correct answers to this question.

Options:

A.

Your role and business partner are assigned to task that have the created status

B.

Your role and business partner are assigned to tasks that have the in process status

C.

Your personal number is not assigned to a business partner

D.

Your user is not assigned to a business partner

Discussion
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Oct 22, 2024
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Question 9

What is a prerequisite for using role charts in project management?

Options:

A.

The demand of a role must have been updated according to tasks

B.

A graphic profile is assigned to the role type

C.

A graphic profile is assigned to the project type

D.

The demand of a role must be distributed over a number of periods

Discussion
Question 10

Your client wants to add additional checklist items to aprojectthat has already began. They want to control the items separately as unplanned.

Which setting must you make in customizing?

Options:

A.

Create a checklist type and assign a new status Unplanned

B.

Create a checklist item type and set the issue item indicator

C.

Create a checklist item type and assign to the project type

D.

Create a checklist type and set the issue list indicator

Discussion
Question 11

Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?

NOTE: There are 3 correct answers to this question

Options:

A.

Phase

B.

Task

C.

Role

D.

Checklist item

Discussion