SAP Updated C_TS412_2021 Exam Questions and Answers by jannah

Page: 2 / 3

SAP C_TS412_2021 Exam Overview :

Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Exam Code: C_TS412_2021 Dumps
Vendor: SAP Certification: SAP Certified Application Associate
Questions: 110 Q&A's Shared By: jannah
Question 8

Where do you control whether a project stock is managed as valuated or non-valuated project stock?

Options:

A.

In the network activity

B.

In the project definition

C.

In the WBS element

D.

In the material master

Discussion
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Oct 5, 2024
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Question 9

Which organizational structures are required for network activities? Note: There are 3 correct answers to this question

Options:

A.

Controlling area

B.

Plant

C.

Sales organization

D.

Company code

E.

Operating concern

Discussion
Question 10

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

Options:

A.

The network profile

B.

The control key

C.

The table of MRP controllers

D.

The scheduling parameters for the network

Discussion
Question 11

Cost and Budget

What function are available for period end-closing in the project System?

Options:

A.

Result analysis

B.

Progress analysis

C.

Milestone trend analysis

D.

Settl ement

E.

Confirmation

Discussion