SAP C_TPLM22_67 Exam Overview :

Exam Name: SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Exam Code: C_TPLM22_67 Dumps
Vendor: SAP Certification: SAP Certified Application Associate
Questions: 165 Q&A's Shared By: cassius
Question 16

Based on which of the following the checking control function determines whether an order type will be checked and if so, which checking rules should be used?

Please choose the correct answer.

Response:

Options:

A.

Status

B.

Scope

C.

Group

D.

Check indicator

Discussion
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Nov 7, 2025
Me too. They're a lifesaver!
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Nov 18, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Nov 9, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Nov 1, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 17

Which of the following master data fields of an internally processed activity have an impact on capacity requirements? Choose the correct answers (3)

Options:

A.

Usage

B.

Work

C.

Activity type

D.

Work center

E.

Duration

Discussion
Question 18

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?

Please choose the correct answer.

Response:

Options:

A.

Deviations

B.

Time gaps

C.

Floats

D.

High priority

Discussion
Question 19

Which of the following specifies how much time must elapse between individual archiving steps in network type?

Please choose the correct answer.

Response:

Options:

A.

Functional areas

B.

Residence times

C.

Classification indicator

D.

Functional areas

Discussion