Black Friday Special: Limited Time 80% Discount Offer! Use coupon code below to save on all exam bundles! - Ends in 0d 00h 00m 00s - Coupon code: cram80

PMI Updated PMI-PBA Exam Questions and Answers by antonio

Page: 3 / 14

PMI PMI-PBA Exam Overview :

Exam Name: PMI Professional in Business Analysis
Exam Code: PMI-PBA Dumps
Vendor: PMI Certification: PMI Professional in Business Analysis
Questions: 200 Q&A's Shared By: antonio
Question 12

When a change request is received, the business analyst is responsible for:

Options:

A.

analyzing the impact to the project schedule and budget.

B.

ensuring that change-related incidents are minimized in production.

C.

analyzing the impact on business and underlying systems.

D.

prioritizing and scheduling the changes requested.

Discussion
Question 13

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

Options:

A.

Decomposition model

B.

Context diagram

C.

Swimlane diagram

D.

Business analysis work plan

Discussion
Question 14

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

Options:

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Discussion
Question 15

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Discussion
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Oct 26, 2026
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Oct 16, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Oct 20, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Oct 21, 2026
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Oct 12, 2026
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Page: 3 / 14

PMI-PBA
PDF

$39.8  $199

PMI-PBA Testing Engine

$45  $225

PMI-PBA PDF + Testing Engine

$49.8  $249