Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMI-PBA Exam Questions and Answers by antonio

Page: 3 / 14

PMI PMI-PBA Exam Overview :

Exam Name: PMI Professional in Business Analysis
Exam Code: PMI-PBA Dumps
Vendor: PMI Certification: PMI Professional in Business Analysis
Questions: 200 Q&A's Shared By: antonio
Question 12

When a change request is received, the business analyst is responsible for:

Options:

A.

analyzing the impact to the project schedule and budget.

B.

ensuring that change-related incidents are minimized in production.

C.

analyzing the impact on business and underlying systems.

D.

prioritizing and scheduling the changes requested.

Discussion
Question 13

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

Options:

A.

Decomposition model

B.

Context diagram

C.

Swimlane diagram

D.

Business analysis work plan

Discussion
Question 14

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

Options:

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Discussion
Question 15

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Discussion
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 11, 2026
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 19, 2026
That sounds really useful. I'll definitely check it out.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Sep 27, 2026
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Sep 16, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Sep 10, 2026
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Page: 3 / 14

PMI-PBA
PDF

$59.7  $199

PMI-PBA Testing Engine

$67.5  $225

PMI-PBA PDF + Testing Engine

$74.7  $249