Black Friday Special: Limited Time 80% Discount Offer! Use coupon code below to save on all exam bundles! - Ends in 0d 00h 00m 00s - Coupon code: cram80

PMI Updated PMI-PBA Exam Questions and Answers by antonio

Page: 3 / 14

PMI PMI-PBA Exam Overview :

Exam Name: PMI Professional in Business Analysis
Exam Code: PMI-PBA Dumps
Vendor: PMI Certification: PMI Professional in Business Analysis
Questions: 200 Q&A's Shared By: antonio
Question 12

When a change request is received, the business analyst is responsible for:

Options:

A.

analyzing the impact to the project schedule and budget.

B.

ensuring that change-related incidents are minimized in production.

C.

analyzing the impact on business and underlying systems.

D.

prioritizing and scheduling the changes requested.

Discussion
Question 13

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

Options:

A.

Decomposition model

B.

Context diagram

C.

Swimlane diagram

D.

Business analysis work plan

Discussion
Question 14

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

Options:

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Discussion
Question 15

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Discussion
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Oct 20, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 18, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Oct 14, 2026
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Oct 20, 2026
YES….. I saw the same questions in the exam.
Page: 3 / 14

PMI-PBA
PDF

$39.8  $199

PMI-PBA Testing Engine

$45  $225

PMI-PBA PDF + Testing Engine

$49.8  $249