Question 12

You have to review the following user story that will be developed and tested during the next

Sprint:

As a potential conference attendee, I want to be able to register for the conference online, so that

registration is simple and paperless.

The following acceptance criteria are also mentioned:

i) Payment can be made via PayPal, Debit or Credit Cards

ii) An acknowledgement email is sent to the attendee after submitting the form

iii) Protection against spam is working as expected

iv) Information from the form is stored in the registrations database

v) All incorrect user inputs are flagged by the system

Which of the following correctly shows which acceptance criteria are testable?

Options:

A.

ii, iv, v are testable

B.

i, iii, v are testable

C.

i, ii, iv are testable

D.

iii, iv, v are testable

Discussion
Question 13

“As the leader of the marketing department, I want to have a content management system so that

my employees can edit and provide quality content to the readers”

Which of the following requirements engineering techniques would be the MOST effective for

identifying and prioritizing user stories for the given Epic?

Options:

A.

Storyboarding

B.

Story mapping

C.

Defining Personas

D.

Class Diagrams

E.

Use Cases

Discussion
Question 14

You have been working as a tester in an Agile team You have found that the user stories are being defined by the team but it is still unclear what will be a successful outcome Even after story elaboration you are still unclear as to what a story should do As a result, you're not really sure what to test or to know when you'll be done with testing This problem is becoming worse as completed stories are showcased but the product owner is unhappy with the results

You've looked into the matter further and the comments from the product owner indicate that features are missing from the stories. The story is functioning correctly within the limited definition of the story but the product owner is expecting more functionality, such as error handling that isn't being defined in the story

What technique should you implement that would help to further define the product owner's expectations and alleviate the issues that are arising during the show cases?

Options:

A.

TDD by the developers before they begin coding

B.

BDD by the developers when unit tests are being created

C.

ATDD by the team to better define the requirements

D.

A combination of TDD and BDD by the team to improve the pre-build testing

Discussion
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 18, 2024
That sounds really useful. I'll definitely check it out.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Question 15

Which of the following correctly describes positive characteristic of unit tests?

Options:

A.

Unit tests should be independent from system components other than the one to be tested

B.

Unit test can be derived from the given epics and existing code of the test object

C.

While refactoring, the redesign of the unit test to adapt to the changed code is crucial

D.

A unit test should be written against large and complex code structures to get fast and

feedback of the code quality