Question 20

A company, which is heavily reliant on its IT systems, experiences a critical problem affecting its just-in-time processes. The manager recognises an immediate need to change and upgrade systems, which he knows will meet resistance by some long serving staff.

 

Which of the following would be the most appropriate method for dealing with the resistance at this time?

Options:

A.

Coercion

B.

Facilitation

C.

Participation

D.

Negotiation

Discussion
Question 21

The balanced scorecard involves creating a set of measures for which THREE of the following perspectives?

Options:

A.

Financial: How should we appear to our shareholders?

B.

Learning and Growth: To achieve our vision, how will we sustain our ability to change and improve?

C.

Quality: How do we improve our product and service quality to outpace the competition?

D.

Customers: To achieve our vision, how should we appear to our customers?

E.

Productivity: How do we improve our rate of output to satisfy all our stakeholders?

Discussion
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Sep 14, 2024
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 25, 2024
Good point. Thanks for the advice. I'll definitely keep that in mind.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 29, 2024
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Question 22

Max is a quiet member of staff who likes to receive all the details before making decisions in the workplace.

 

He is very satisfied with the way he works currently and is reluctant to change the way he works when you suggest implementing a new system to deal with enquiries. These changes form a major part of his work allocation.

 

Which would be the most appropriate methods to deal with any resistance to change you may experience from Max?

 

Select ALL that apply.

Options:

A.

Coercion

B.

Manipulation / Co-optation

C.

Participation / involvement

D.

Education

E.

Facilitation / support

F.

Negotiation / agreement

Discussion
Question 23

J has been appointed project manager for a multimillion dollar upgrade to factory computer systems for his international organisation.

 

The organisation has decided to adopt the PRINCE2 project management methodology, of which J has knowledge from a previous post, but this was some time ago and his knowledge may need updating.

 

In order to achieve maximum success, J realises he will need to ensure that problems encountered at each phase of the project are used to inform later stages of the project.

 

Advise J at which stage of the project lessons learned should be recognised and applied to later stages, in order to prevent recurrence during the project:

Options:

A.

Starting the project

B.

Initiation of the project

C.

Managing stage boundaries

D.

Controlling a stage