Exam Name: | ISTQB Certified Tester Foundation Level CTFL 4.0 Exam | ||
Exam Code: | CTFL4 Dumps | ||
Vendor: | BCS | Certification: | ISTQB Certified Tester |
Questions: | 188 Q&A's | Shared By: | aras |
During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time.
The team agreed on the following:
1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra-large, and Extra-extra-large.
2. If estimation values differ significantly, the highest score will be used for estimation purposes.
The result of the first round of planning poker:
Team MemberEstimation
BusinessLarge
DevelopmentExtra-extra-large
TestingExtra-extra-large
Which of the following options best represent the team’s next actions?
Consider the following list of possible benefits of retrospectives (A to D):
The fact that defects are usually not evenly distributed among the various modules that make up a software application, but rather their distribution tend to reflect the Pareto principle: