SAP Certified Application Associate SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7

SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7

Last Update Feb 18, 2025
Total Questions : 106

To help you prepare for the C_TSCM42_67 SAP exam, we are offering free C_TSCM42_67 SAP exam questions. All you need to do is sign up, provide your details, and prepare with the free C_TSCM42_67 practice questions. Once you have done that, you will have access to the entire pool of SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 C_TSCM42_67 test questions which will help you better prepare for the exam. Additionally, you can also find a range of SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 resources online to help you better understand the topics covered on the exam, such as SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 C_TSCM42_67 video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic SAP C_TSCM42_67 exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.

Which BOM item category must you set to fulfill this requirement?

Options:

A.  

D (document item)

B.  

E (external procurement)

C.  

M (phantom material)

D.  

N (non-stock item)

Discussion 0
Questions 3

Which of the following structural elements does a process order have? (Choose three.)

Options:

A.  

Item data

B.  

Parallel sequences

C.  

Relationships

D.  

Phases

E.  

Characteristic-based process instructions

Discussion 0
Questions 4

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.

What does a firming type define? (Choose two)

Options:

A.  

Handling existing procurement proposals outside the planning time fence.

B.  

Handling existing procurement proposals within a planning time fence.

C.  

Handling new requirements within the planning time fence.

D.  

Handling new procurement proposals that need to be created due to new requirements within the planning time fence.

Discussion 0
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Nell
Are these dumps reliable?
Ernie Oct 10, 2024
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Robin
Cramkey is highly recommended.
Jonah Oct 16, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Questions 5

You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.

How can you fulfill these requirements in SAP ECC? (Choose two)

Options:

A.  

Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.

B.  

Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

C.  

Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

D.  

Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

Discussion 0

C_TSCM42_67
PDF

$42  $104.99

C_TSCM42_67 Testing Engine

$50  $124.99

C_TSCM42_67 PDF + Testing Engine