To help you prepare for the C_TS422_2021 SAP exam, we are offering free C_TS422_2021 SAP exam questions. All you need to do is sign up, provide your details, and prepare with the free C_TS422_2021 practice questions. Once you have done that, you will have access to the entire pool of SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2021 test questions which will help you better prepare for the exam. Additionally, you can also find a range of SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing resources online to help you better understand the topics covered on the exam, such as SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2021 video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic SAP C_TS422_2021 exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

How would you define pegging in the context of Advanced Planning?

Options:

A.  

An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements

B.  

An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements

C.  

An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run

D.  

An evaluation to verify if there are material or capacity shortages in the network after the production planning run.

Discussion 0
Questions 3

Which materials have a negative quantity in a bill of materials or in a recipe?

Options:

A.  

Bulk materials

B.  

Co-products

C.  

By-products

D.  

Waste products

E.  

Continuous flow materials

Discussion 0
Questions 4

Where do you maintain data to determine the duration of an operation for production?

Options:

A.  

Bill of material (BOM)

B.  

Routing

C.  

Material master

D.  

Work center

Discussion 0
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Oct 17, 2024
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Oct 22, 2024
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Questions 5

What does it mean for the production planner when MRP works with infinite capacities?

Options:

A.  

MRP assigns capacity requirements automatically after the last scheduled order on a work center.

B.  

MRP creates capacity requirements without checking the capacity of a work center.

C.  

MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

D.  

MRP creates capacity requirements only if the work center has sufficient capacity.