Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-RMP Exam Questions and Answers by magnus

Page: 9 / 15

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 221 Q&A's Shared By: magnus
Question 36

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.

B.

Determine the workarounds for the program risks and allocate responsibilities to the team.

C.

Allow the most experienced program manager to handle the most critical program risks.

D.

Encourage the program team to assume risk ownership prior to delegation.

 

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 13, 2024
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Sep 28, 2024
did you use PDF or Engine? Which one is most useful?
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 37

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Discussion
Question 38

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact

 

Discussion
Question 39

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Discussion
Page: 9 / 15

PMI-RMP
PDF

$36.75  $104.99

PMI-RMP Testing Engine

$43.75  $124.99

PMI-RMP PDF + Testing Engine

$57.75  $164.99