CAPM Certified Associate in Project Management (CAPM) Certification

Certified Associate in Project Management (CAPM) Certification

Last Update May 19, 2024
Total Questions : 748

To help you prepare for the PMI-002 PMI exam, we are offering free PMI-002 PMI exam questions. All you need to do is sign up, provide your details, and prepare with the free PMI-002 practice questions. Once you have done that, you will have access to the entire pool of Certified Associate in Project Management (CAPM) Certification PMI-002 test questions which will help you better prepare for the exam. Additionally, you can also find a range of Certified Associate in Project Management (CAPM) Certification resources online to help you better understand the topics covered on the exam, such as Certified Associate in Project Management (CAPM) Certification PMI-002 video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic PMI PMI-002 exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 4

Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?

Options:

A.  

CPM

B.  

PERT

C.  

Schedule simulation

D.  

Path convergence method

Discussion 0
Questions 5

Which of the following statements are FALSE about the Rolling Wave plan?

Options:

A.  

Rolling Wave Planning is a phased iterative approach to project development.

B.  

Rolling Wave Planning is a cost and schedule planning technique used in the Define Activities process.

C.  

Rolling Wave Planning is the process of decomposing each work package within the WBS into the corresponding schedule activities required to produce the work package deliverables.

D.  

Rolling Wave Planning describes a form of progressive elaboration planning where the work to be performed in the near time is planned in detail at a low level of the WBS, while work far in future is planned for WBS components that are relatively at a high level of WBS.

Discussion 0
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan (not set)
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander (not set)
Thanks for the recommendation! I'll check it out.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden (not set)
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse (not set)
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella (not set)
That's great. I think I'll give Cramkey Dumps a try.
Questions 6

A technique for resolving conflict in which the parties agree to have a neutral third party hear the dispute and make a decision is called ____________.

Options:

A.  

Negotiation

B.  

Arbitration

C.  

Smoothing

D.  

Forcing

Discussion 0
Questions 7

A schedule activity may start 5 days before the predecessor activity finishes. This is an example of ______________.

Options:

A.  

Finish-to-Start

B.  

Finish-to-Finish

C.  

Start-to-Start

D.  

Start-to-Finish

Discussion 0